Bill of Quantity vs Schedule of Works - boards.ie
www.boards.ie › discussion › 2057906001Aug 28, 2018 · shianto. I have had a conversation with my QS about whether or not to use a Bill of Quantities in our tender. He has stated he does a very detailed Schedule of Works and does not feel the need to do a Bill of Quantity, but he has said if I want to pay for the BoQ he will do the work. From the preliminary costing we are talking a build cost of ...
Rates and quantities on an activity schedule - NEC Contract
www.neccontract.com › support › faqsThere should be no rates or quantities in an activity schedule. Instead it is, as the names implies, a series of activities with a lump-sum price for each, see clause 11.2 (30). Your subcontractor gets paid for each activity once it is completed, see clause 11.2 (27). There is no method of measuring the works or accommodating what is effectively a bill of quantities in ECS option A.